Question: What’s is the status on the passenger terminal security and access improvement project at Hancock International Airport?
Syracuse (WSYR-TV) – Question: What’s is the status on the passenger terminal security and access improvement project at Hancock International Airport?

Answer: Airport Commissioner Chris Callahan says several phases of the project are underway.

The exterior canopies for the north and south terminals are being extended, while the center lobby and main entrance door are being widened.

Electrical and mechanical work associated with the HVAC system is also underway.

New restrooms on the second floor are being completed and new baggage belts are being installed.

They expect to complete the project by early fall.